Sanitary Sewer System Rehabilitation Project
|
Project Information
A three year Sanitary Sewer Evaluation Study was conducted by RJN from FY2008 to FY2010. The final report from the SSES recommended the rehabilitation of 358 sewer manholes including replacing manhole rings/lids, corbel, invert, clean-out, and point repairs, as well as street and pavement repairs resulting from activities associated with conducting the manhole repairs. These repairs were recommended in order to prevent Inflow and Infiltration of stormwater and ground water which should lower the City's treatment costs to TRA. This project will be completed over three fiscal years.
Project Details
Engineering Consultant:
|
RJN
|
Contractor:
|
City of Southlake Wastewater Utility Division
|
Budget:
|
- Yr. 1 (FY 2012) - $100,000
- Yr. 2 (FY 2013) - $250,000
- Yr. 3 (FY 2014) - $250,000
Total - $600,000 |
Construction Start Date:
|
2012
|
Anticipated Completion Date:
|
2015
|
Staff Contact:
|
Jack Thompson
|
Title:
|
Wastewater Supervisor
|
Phone Number:
|
(817) 748-8082
|
For further information on this project, please see the "Public Works Capital Projects" quarterly report.
Return to the Active City Construction Projects page. |
|
|