Pearson Ground Storage Tank #1 and #2 Repaint
Project Information
This project involves repainting the interior of Pearson ground storage tank #1 and the exterior of Pearson ground storage tank #2. The existing coatings are the original coatings that were installed at the time of tank construction in 1999 so they are going to be repainted to address issues of interior pitting and exterior oxidization.
Project Details
Engineering Consultant: |
Neel Schaffer |
Construction Contractor: |
MK Painting, Inc |
Budget: |
$1,000,000 |
Construction Start Date: |
Fall 2014 |
Anticipated Completion Date: |
Spring 2015 |
Status: |
In Progress |
Staff Contact: |
Om Gharty Chhetri, P.E. |
Title: |
Civil Engineer |
Phone Number: |
(817) 748-8089 |
For a more detailed description of this project, please see the "
Public Works Capital Projects Update" quarterly report.