Shady Oaks Dr Utility & Roadway Improvements
Shady Oaks - dove to highland.JPG

Project Information
This project will implement utility improvements beginning at the north property line of Durham Elementary South to the intersection of Fox Glen and Shady Oaks Dr. These improvements will include:
  • An 8" sanitary sewer line from Highland St. to Fox Glen along Shady Oaks Dr.
  • A 12" water line from Highland St. to Fox Glen along Shady Oaks Dr.

Project Details
Engineering Consultant:
MLA Consulting
Contractor:
TBD
Budget:
$1,250,000
Construction Start Date:
2015
Anticipated Completion Date:
2015
Status:
  • Council approved this project as part of the FY 2013 budget on September 18, 2012.
  • Construction schedule TBD based on area impact in conjunction with other projects.
  • Design for this project is currently at 90%.
    Staff Contact:
    Alex Ayala, P.E.
    Title:
    Civil Engineer
    Phone Number:
    (817) 748-8274

    For further information on this project, please see the "Public Works Capital Projects" quarterly report. 

    Return to the Active City Construction Projects page.