8-inch Water Line connector from Lake Dr/Burney Ln to Palo Duro/Lonesome Dove
|
Project Information
This project involves funding to connect an 8-inch water line at Lake Dr. and Burney Ln. to the existing 6-inch waterline at Palo Duro and Lonesome Dove by installing 1600 feet of 8-inch PVC. The new line will provide increased water pressure and flow, and will establish a loop for fire protection to the Dove Estates Subdivision.
Project Details
Engineering Consultant: |
MLA Consulting |
Construction Contractor: |
TBD |
Budget: |
$350,000 |
Construction Start Date: |
2014 |
Anticipated Completion Date: |
2014 |
Southlake 2030 Comprehensive Master Plan Item: |
T2-13 |
Status: |
An engineering design contract with MLA Consulting was approved at the November 6, 2012 City Council meeting. |
Staff Contact: |
Alex Ayala, P.E. |
Title: |
Civil Engineer |
Phone Number: |
(817) 748-8274 |
For a more detailed description of this project, please see the "Public Works Capital Projects Update" quarterly report.
Return to the Active City Construction Projects page. |
|
|